This Monday, April 2, EDF has come we connect the control panel. We had a cabinet construction throughout the building, but now we'll use a little more power for the commissioning of hot frames scheduled for that week.
We pulled a cable 4G25 (25 mm ² per conductor) in the box located in EDF property line to our switchboard on twenty meters. We also took with him a cable for remote reading.
We pulled a cable 4G25 (25 mm ² per conductor) in the box located in EDF property line to our switchboard on twenty meters. We also took with him a cable for remote reading.